Medak–Akkannapet section

From Wikipedia, the free encyclopedia

Medak–Akkannapet section
Overview
StatusOperational
OwnerIndian Railways
LocaleTelangana
Termini
Service
Operator(s)South Central Railway
Technical
Track length17.2 km (10.7 mi)
Track gauge5 ft 6 in (1,676 mm) broad gauge
Route map

Kacheguda–Manmad section

Akkannapet
Laxmapur
Shamnapur
Medak
Source: indiarailinfo.com

The Medak–Akkannapet section is an operational railway line of the Indian Railways.[1] The section falls under the jurisdiction of Hyderabad of South Central Railway zone.[2][3]

The project[edit]

The project was sanctioned in the year 2012–13.[1] The foundation was laid on 19 January 2014 at Medak by Vijayashanthi (MP).[4] The total length of the section is 17.2 km (10.7 mi) and the total cost of the project is 1.293 billion (US$16 million).[5]The Project was inaugurated in september 2022.[6]

References[edit]

  1. ^ a b "Surveys" (PDF). South Central Railway, Indian Railways. 24 July 2015. p. 2. Retrieved 3 May 2019.
  2. ^ Wait for new rail lines in T gets longer
  3. ^ Akkannapet to Medak railway line by March 2019
  4. ^ "Foundation Stone laid for a new Railway line between Akkannapet-Medak – RailNews Media India Ltd". www.railnews.co.in. Archived from the original on 3 June 2016. Retrieved 20 May 2016.
  5. ^ Avadhani, R (18 January 2014). "Medak-Akkannapet railway line works to begin soon". The Hindu. Retrieved 20 May 2016.
  6. ^ "Kishan Reddy dedicates a new railway line between Medak - Akanapet to the nation". 23 September 2022.