Busitema Solar Power Station

Coordinates: 00°32′50″N 34°01′25″E / 0.54722°N 34.02361°E / 0.54722; 34.02361
From Wikipedia, the free encyclopedia

Busitema Solar Power Station
Map
CountryUganda
LocationBusia District
Coordinates00°32′50″N 34°01′25″E / 0.54722°N 34.02361°E / 0.54722; 34.02361
StatusOperational
Construction began2018
Commission date2022
Construction costUS$6.5 million
Owner(s)Busitema University
Operator(s)Busitema University
Solar farm
TypeFlat-panel PV
Site area7.5 hectares (19 acres)
Power generation
Nameplate capacity4 megawatts (5,400 hp)

The Busitema Solar Power Station is a 4 megawatts (5,400 hp) solar power plant in Uganda.[1]

Location[edit]

The power station is located in Busia District in the Eastern Region of Uganda, on the main campus of Busitema University,[2] a public university, approximately 183 kilometres (114 mi), by road, east of Kampala, the largest city and capital of Uganda.[3]

Overview[edit]

This solar station is a donation from the government of Egypt to the government of Uganda. This followed the signing of bilateral agreements between the two countries in 2016.[1] This was then followed by the signing of a memorandum of understanding between Abdel Fattah el-Sisi, the president of Egypt, and Yoweri Museveni, the president of Uganda, in May 2018.[4] The power station is intended to increase Uganda's renewable energy pool, increase the supply of power to the Eastern Region, and serve as a teaching tool to university students studying renewable energy programs.[1]

This power station was the fifth solar power station connected to the Ugandan national electricity power grid, after the Soroti Solar Power Station, which came online in December 2015, the Tororo Solar Power Station, which was commissioned in October 2017,[5] and the Kabulasoke Solar Power Station, which was commissioned in December 2018.[2] Mayuge Solar Power Station with capacity of 10 megawatts came online in June 2019.[6]

Developers[edit]

The solar power plant was developed by engineers from the Egyptian Ministry of Electric & Renewable Energy Authority. The senior engineer is Mohammed A. Abdel Aziz and the project manager is engineer Reda Shaban Ali. An Egyptian team, led by the two, performed an advance inspection and approved the site of the plant.[1]

The parties agreed for Egypt to provide the necessary equipment and engineering services while Uganda provides the 7.5 hectares (19 acres) real estate where the plant is built. In addition, Uganda catered for the ground transportation and taxation of the donated equipment, from the port of Mombasa, Kenya to the project location in Uganda.[4]

Commissioning[edit]

The completed power station was commissioned by the Energy Minister at that time, Ruth Nankabirwa and the First Deputy Prime Minister and Minister for the East African Community, Rebecca Kadaga, on 25 January 2022.[7]

See also[edit]

References[edit]

  1. ^ a b c d Abraham Mutalyebwa (14 August 2018). "Egyptian Government Donates 4MW Solar Power Project to Uganda". PMLDaily.com. Kampala. Retrieved 15 August 2018.
  2. ^ a b Philip Wafula (22 October 2019). "Busitema University To Add 4MW of Solar Power". Daily Monitor. Kampala. Retrieved 24 October 2019.
  3. ^ Google (6 February 2022). "Distance Between Bank of Uganda, Kampala Road, Kampala, Uganda And Busitema University, Main Campus, Tororo Road, Busia District, Uganda" (Map). Google Maps. Google. Retrieved 6 February 2022.
  4. ^ a b Apollo Mubiru (9 May 2018). "Uganda, Egypt Sign Energy, Agriculture Pact". New Vision. Kampala. Retrieved 15 August 2018.
  5. ^ John Green (15 August 2018). "Egypt Prepares 4MW Solar Power Project for Uganda's Renewable Energy". Dar es Salaam: The Exchange. Retrieved 15 August 2018 – via AllAfrica.com.
  6. ^ Electricity Regulatory Authority (17 June 2019). "Uganda's Grid-Connected Solar Portfolio Increases". Electricity Regulatory Authority. Kampala, Uganda. Retrieved 6 February 2022.
  7. ^ John Odyek (25 January 2022). "Kadaga, Nankabirwa launch Busitema solar project". Bukedde Newspaper Uganda. Kampala, Uganda. Retrieved 6 February 2022.